2013 — Annual Schedule 128 Transition Adjustment
2013 PGE COS Energy Rate — 2013 Market Rate = Transition Adjustment
The Schedule 128 transition adjustment is only applicable to customers that selected a market option (direct access or Daily pricing).
| Schedule |
|
COS Energy Price (¢/kWh) |
Market Value of Energy (¢/kWh) |
Transition Adjustment (¢/kWh) |
| 515 |
|
5.174 |
3.243 |
1.931 |
| 532 |
|
6.032 |
3.537 |
2.495 |
| 538 |
|
5.743 |
3.464 |
2.279 |
| 549 |
|
6.543 |
3.290 |
3.253 |
| 83/583-S |
|
5.913 |
3.517 |
2.396 |
| 85/585-S |
On Peak |
5.875 |
3.862 |
2.013 |
| |
Off Peak |
5.118 |
2.863 |
2.255 |
| 89/589-S |
On Peak |
5.726 |
3.875 |
1.851 |
| |
Off Peak |
4.969 |
2.886 |
2.083 |
| 85/585-P |
On Peak |
5.698 |
3.743 |
1.955 |
| |
Off Peak |
4.941 |
2.790 |
2.151 |
| 89/589-P |
On Peak |
5.555 |
3.749 |
1.806 |
| |
Off Peak |
4.798 |
2.786 |
2.012 |
| 89/589-T |
On Peak |
5.481 |
3.684 |
1.797 |
| |
Off Peak |
4.724 |
2.745 |
1.979 |
| 91/591 |
|
5.174 |
3.243 |
1.931 |
| 592/594 |
|
5.244 |
3.433 |
1.811 |
|
- Annual Schedule 128 Transition Adjustment prices are only applicable to above Schedules and for Customers leaving Annual COS pricing during the November 2012 open enrollment window.
- Posted prices are effective January 1, 2013 through December 31, 2013.
- Posted COS Energy Prices include Schedule 125 (Annual Update), which is an estimate and subject to Commission approval.
- These charges do not reflect your total bill. They do not include other charges such as basic charge, distribution, transmission and system usage charges or supplemental adjustments.
2013 — 9-month Balance of Year Schedule 128 Transition Adjustment
2013 PGE COS Energy Rate — 9 Months Balance of Year Market Rate = 9 Months Balance of Year Transition Adjustment
The Schedule 128 transition adjustment is only applicable to customers that selected a market option (direct access or Daily pricing).
| Schedule |
|
COS Energy Price (¢/kWh) |
Market Value of Energy (¢/kWh) |
Transition Adjustment (¢/kWh) |
| 538 |
|
5.750 |
3.339 |
2.411 |
| 83/583-S |
|
5.913 |
3.387 |
2.526 |
| 85/585-S |
On Peak |
5.875 |
3.713 |
2.162 |
| |
Off Peak |
5.118 |
2.765 |
2.353 |
| 89/589-S |
On Peak |
5.726 |
3.722 |
2.004 |
| |
Off Peak |
4.969 |
2.789 |
2.180 |
| 85/585-P |
On Peak |
5.698 |
3.600 |
2.098 |
| |
Off Peak |
4.941 |
2.685 |
2.256 |
| 89/589-P |
On Peak |
5.555 |
3.603 |
1.952 |
| |
Off Peak |
4.798 |
2.697 |
2.101 |
| 89/589-T |
On Peak |
5.481 |
3.540 |
1.941 |
| |
Off Peak |
4.724 |
2.649 |
2.075 |
| 91/591 |
|
5.174 |
3.088 |
2.086 |
| 592/594 |
|
5.244 |
3.302 |
1.942 |
|
- 9-month Balance of Year Schedule 128 Transition Adjustment prices are only applicable to above Schedules and for Customers leaving Annual COS pricing during the February 2013 election window.
- Posted prices are effective April 1, 2013 through December 31, 2013.
- Posted COS Energy Prices include Schedule 125 (Annual Update).
- These charges do not reflect your total bill. They do not include other charges such as basic charge, distribution, transmission and system usage charges or supplemental adjustments.
Change your pricing plan selection
If you participated in the February election window, and opted to leave cost of service, you will default to Daily pricing unless a DASR is received.
The next opportunity to modify your pricing plan selection will be during the September election window, which will be open from Sept. 1 through 5 p.m. Sept. 28. During this window you may choose to leave PGE’s Annual Cost of Service for either a fixed three-year term, or a minimum of five-years. For more information on the September election window read our fact sheet (PDF).
You do not have to do anything to remain on your current pricing plan.