How it works: The process for requesting new or upgraded service

1. Submit request for service form.

Once you have determined which type of service you need, submit your request online and a service and design project manager will review it and get back to you.

The form should include: connected load in kilowatts (kW), load schedule, site plans, landscaping plans, and other critical details so the service and design project manager can complete their review.

Note that the project can’t begin until we receive all your documentation.

2. Obtain any necessary permits.

You will need to get building and electrical permits from the city or county, as well as easements and tree-trimming permits if required.

3. One of our service and design project managers (SDPMs) will contact you shortly after we receive your request.

The project can’t begin until we receive complete documentation. Your SDPM will outline what’s needed based on your specific project.

Once we have all your documents, we will design service for your site, which may take up to 60 days depending on the specifics of the project.

4. Arrange a pre-construction meeting.

Once you have worked with your project manager to design service, contact us to arrange a pre-construction meeting between the excavation contractor and us at the site.

5. Complete trench, vault and conduit work.

Before digging a trench, consult our trench checklist for residential or commercial construction and check with your assigned project manager for design approval.

Call 811 or visit Call Before You Dig to locate existing underground utilities before digging. This service is free.

Right-of-way excavation must be performed by a PGE approved contractor. Your SDPM can supply you with information about approved contractors in your area.

6. We inspect all services, trenches and conduits, and then complete construction of electrical service and install the meter.

After all construction work is completed and we inspect and approve the design and work, we will schedule the connection of service within 5 to 10 business days.

Get started: Submit your request for service

After you submit your form, we’ll email you shortly with further information and instructions.

Request for temporary service

You can request temporary electric service from us for your project. Learn more about temporary electric service options.

Frequently asked questions: Do I need an easement?

Some electric facilities that are on property not owned by you or PGE, may require an easement.

You are responsible for easement payments, though we are available to assist you with writing and recording the easements you need.

We are available to assist you in writing and recording any required easements.